Judge sides with Florida in fight over federal contractor vaccination mandate

“The extent of any absenteeism attributable to COVID-19 among contractors and subcontractors is unexplained,” Merryday wrote. “The frequency and duration of any procurement delay attributable to COVID-19 is unexplained. The extent of any cost increases attributable to COVID-19 is unexplained. In other words, the extent of any procurement problem, past or future, attributable to COVID-19 is undemonstrated and is merely a hastily manufactured but unproven hypothesis about recent history and a contrived speculation about the future. Obviously, no massive extension and expansion of presidential power is necessary to cure a non-existent problem and certainly neither ‘good cause’ nor ‘urgent and compelling circumstances’ exists to justify summary disregard of the requirements of administrative law and rulemaking.”